Client
Los Lunas
Completion
2009
Size
Two Dams (Over 50 acre-feet Each)
Cost
$1.1 million
Molzen Corbin acted as the Engineer Supervising Construction for this $1.1-million flood control project, which was designed to protect the Village of Los Lunas against flows from a nearby arroyo. Project elements included two dams of over 50 acre-feet each, berms, and drainage channelization. The project also included soil-cement spillways, drop structures, and several training dykes, each more than one mile long to direct flows into the dams.
Scope of Work
Drainage Engineering
Share this Post